The Service Technician Is About to Open Your Machine: What 1910.147(f)(2) Expects From You Before They Touch a Lock
When an outside technician services your equipment, 29 CFR 1910.147(f)(2) requires both employers to swap lockout procedures. Here is what to do first.
The compressor tech arrives at seven in the morning with a tablet, a tool bag, and a service ticket. Your machine has been throwing a fault for three days. You walk him to the unit, say "it's all yours," and go back to the front counter. Twenty minutes later he is reaching into a guard opening, and nobody on your side can say who has isolated the power, which lock is on the disconnect, or whether the unit has actually stopped storing energy.
Small employers tend to think of lockout/tagout as something their own people do to their own machines. The outside technician, the repair vendor, the HVAC contractor, and the electrician hired for a day all work under their own company's program, and it is easy to assume that program covers everything. It does not cover your equipment, your people, or your liability. The standard has a specific paragraph for this situation, and it puts duties on you as the host.
What 1910.147(f)(2) actually says
The control of hazardous energy standard, 29 CFR 1910.147, applies to servicing and maintenance of machines and equipment where unexpected energization or release of stored energy could injure employees. Paragraph (f) is titled "Outside personnel (contractors, etc.)" and says that whenever outside servicing personnel are engaged in activities covered by the scope and application of the standard, the on-site employer and the outside employer must inform each other of their respective lockout or tagout procedures.
That is a two-way obligation. You tell the contractor how your machine is isolated and what your rules are. The contractor tells you how their technicians lock out. The same paragraph then adds a duty that is easy to miss: the on-site employer must ensure that its own employees understand and comply with the restrictions and prohibitions of the outside employer's energy control program. In plain terms, if the contractor's procedure says nobody enters the area while their lock is on, your employees have to know that and honor it.
Nothing in this paragraph asks you to supervise the technician's work or to become an expert in their trade. It asks for an exchange of information before the work starts, and for your own people to be told what the arrangement is. The failure mode is almost always silence. Neither side has said anything, each assumes the other has it handled, and the first conversation about energy control happens at the machine.
Why the host employer cannot just step back
There are two reasons the information swap matters, and neither is paperwork for its own sake.
The first is physical. Your machine may have more energy sources than the technician expects. A press may have electrical, hydraulic, and pneumatic supplies. A conveyor may be fed by a second line that starts on a timer. A technician who has never seen your plant does not know which disconnect belongs to which machine unless somebody on site tells them, and a mislabeled panel is not a good place to learn it. Your people know where the sources are. The contractor knows what the repair will disturb. Neither can write a safe isolation plan alone.
The second is about who else is around. Your employees are affected employees under the standard, meaning they operate or use the machine, or work in the area where servicing is happening. 1910.147(c)(7) requires that affected employees be instructed on the purpose and use of the energy control procedure, and that all other employees whose work may be in the area understand the prohibition against restarting or re-energizing locked or tagged equipment. If the contractor locks a disconnect and your operator, seeing the machine down, flips a different switch or removes a tag because it looks like it was left behind, the injury will not be the contractor's alone. Under OSHA's multi-employer citation policy, more than one employer on a site can be cited for the same hazard, and a host that neither communicated nor controlled access is hard-pressed to argue it had nothing to do with the outcome.
A short exchange that works for a small shop
You do not need a thirty-page contractor program. You need a repeatable ten-minute conversation, ideally before the day of the visit and confirmed in writing, even if "in writing" is an email reply.
Start by identifying the equipment and its energy sources. Say which disconnects, valves, and breakers feed it, where they are, and which of them are hard to see or serve more than one machine. Walk the technician to each isolation point rather than describing it. If you have a written machine-specific procedure, hand it over. Paragraph (c)(4) of the standard expects documented procedures for each machine, with a narrow exception for single-source equipment that meets all of the listed conditions, so a shop that has done this work already has the document to share.
Next, ask for theirs. Ask how the technician applies a lock, whether they carry personal locks, whether they use tags in addition to locks, and how they verify that the energy is gone. The standard's application sequence in (d) runs through preparation for shutdown, shutdown, isolation, application of the device, relieving stored energy, and verification that the machine will not start before work begins. A competent contractor will describe those steps without hesitation. If the answer is that they just turn it off, that is useful information, and it is better to have it before the hood is open.
Then decide who holds what. Agree on whose locks go on which isolation points, and where the contractor's lock sits relative to yours. If your own maintenance person is also working on the unit, the lockout device should accommodate more than one lock, with every person who is exposed placing their own. Do not let a single lock stand in for two people's protection, and do not let anyone but the person who applied a lock remove it. The release steps in (e) require that the work area be inspected, that employees be clear, and that affected employees be notified before locks come off and the machine is restored.
Finally, tell your own crew. A short word at the start of the shift is enough: this unit is being serviced by an outside company, their locks are on these points, nobody touches those switches, and the area around it is closed until someone comes to tell you otherwise. That sentence is the compliance step for the second half of (f)(2).
The cases that slip through
The routine service call is not the only one. A delivery driver who adjusts equipment, a vendor refilling a machine that has moving parts, a utility crew working on a feed to your building, and a facilities contractor changing lighting over a conveyor can each raise the same question. The test is whether their work falls within the standard's scope: servicing or maintenance where unexpected startup or release of stored energy is possible. If it does, the exchange of procedures applies, whether the person is on the clock for ten minutes or ten days.
Two other situations catch small shops. One is the contractor who arrives and finds your equipment poorly labeled, with no documented procedure. They may lock out as best they can, and the shop is left with a visit that exposed a program gap without fixing it. Use the visit as a prompt. Write the procedure afterwards, while the machine and the technician's notes are fresh. The other is a job that runs across a shift change. The standard expects continuity of protection when personnel change, which means the contractor's lock stays on until the contractor's person removes it, not until your closing manager decides the job must be finished.
Keeping a record of the handoff
The standard does not prescribe a form for the information swap, so what you keep is your own call. A reasonable record is a single page signed or acknowledged by both parties that lists the equipment, the energy sources and isolation points, who applied locks and when, who was notified in your plant, and who removed locks and confirmed restoration. It takes a few minutes to complete. It also becomes the answer when an inspector asks how you coordinate with outside servicing personnel, and a reviewer asking about your periodic inspection under (c)(6) will find that outside visits are a good test of whether the written procedure matches the real machine.
If you are building or tightening the machine-specific procedure that this handoff relies on, our lockout/tagout procedures template includes a machine-specific procedure sheet and a periodic-inspection log. It is a working document, not a substitute for reading the standard or for a procedure that fits your actual equipment.
Before the next service call
Look at your calendar for the next outside visit to any equipment with moving parts, stored energy, or more than one power source. Pull the machine's written procedure, or write one, and put it in the technician's hands before they start. Ask for theirs. Tell your crew which locks mean stay out. None of that costs money, and each step closes a gap that the standard expects both employers to close together.
Related reading: Lockout Tagout That Technicians Actually Follow | The Annual Lockout/Tagout Inspection: What 1910.147(c)(6) Actually Requires | What 1910.147 Requires: The Six Parts of a Compliant Energy Control Program
OSHA standards cited
- 29 CFR 1910.147
General Industry Standards
Always verify current OSHA standards at osha.gov. This article reflects standards in effect at the date of publication.
Not sure where you stand?
Take the 5-minute compliance assessment. Answer a few questions about your business and get a prioritized list of what OSHA expects, free.
Related Articles
Continue learning about OSHA compliance and workplace safety
Energy Control
The Annual Lockout/Tagout Inspection: What 1910.147(c)(6) Actually Requires
29 CFR 1910.147(c)(6) requires an annual inspection of every energy control procedure. Here's who can conduct it, what it must document, and why shops skip it.
Energy Control
What 1910.147 Requires: The Six Parts of a Compliant Energy Control Program
A clause-by-clause read of 1910.147: written procedures, authorized versus affected employee training, hardware requirements, group lockout, and the annual periodic inspection.
Energy Control
The Minor Servicing Exception and Where It Stops Applying
Clearing a jam, swapping a blade, adjusting a belt — the routine tasks where crews skip lockout, why the minor servicing exception rarely covers them, and how injuries actually happen.