Who Decides the Concrete Is Ready? Stripping Forms and Shores Under OSHA 1926.703

OSHA 1926.703 bars removing forms and shores until the employer determines the concrete is strong enough. See what that rests on and when shoring is inspected.

Updated November 9, 2026
7 min read
By the WorkSafely safety team

It is Friday afternoon. The slab was poured Tuesday, the weather has been good, and the formwork crew is booked on another job Monday. Someone on site says the concrete looks cured and the shores could come out today to keep the schedule. Nobody in that conversation has a test result, and nobody has opened the drawings to see what they say about stripping. The shores come out because it is Friday and the concrete looks hard.

This post answers one narrow question: what does OSHA 1926.703, Requirements for Cast-in-Place Concrete, expect to be true before forms and shores come out, and what does it expect you to do with shoring while the concrete is going in? It sits next to our broader overview of concrete and masonry work under Subpart Q, which covers the whole subpart. Here we stay on formwork, shoring, and the moment of removal, because that is where a small crew's informal habits meet a requirement written in plain terms.

The employer makes the determination, and it has to rest on something

The central sentence is in 1926.703(e)(1). Forms and shores, except those used for slabs on grade and slip forms, shall not be removed until the employer determines that the concrete has gained sufficient strength to support its weight and superimposed loads. The word that matters is "determines." The standard does not say until the concrete is cured, or until a set number of days have passed, or until the foreman is comfortable. It puts the decision on the employer and then says what the decision may be based on.

There are two bases. The first, in (e)(1)(i), is that the plans and specifications stipulate conditions for removal of forms and shores, and those conditions have been followed. If the structural drawings or project specifications say forms stay until a stated strength or a stated condition is met, then the job is to follow that and be able to show you did. The second, in (e)(1)(ii), is that the concrete has been properly tested with an appropriate ASTM standard test method designed to indicate compressive strength, and the test results indicate the concrete has gained sufficient strength to support its weight and superimposed loads.

Notice what is absent. Looking at the surface is not on the list. Neither is calendar time on its own, unless the plans and specifications happen to tie removal to it. For a small contractor, that is the practical lesson. If the project documents give a removal condition, you follow it. If they do not, or you want to strip sooner than they allow, the route the standard gives you is a strength test, and that takes planning before the pour: someone has to arrange for the test, know who will read it, and know that the result has to exist before the shores move.

Reshoring is its own gate

Reshoring is the practice of installing shores under a slab after the original forms and shores come out, so that the new slab is not carrying loads beyond what it can yet bear. The standard treats the removal of that reshoring as a separate decision. Under 1926.703(e)(2), reshoring shall not be removed until the concrete being supported has attained adequate strength to support its weight and all loads in place upon it.

The phrase "all loads in place upon it" is where jobs get into trouble. A floor that was fine when it carried only its own weight may now be holding stacked material, a second pour above it, or equipment. Whoever is deciding whether reshoring can come out needs to know what is actually sitting on the slab at that moment, not what was planned last month. On a small site where material storage moves around daily, that is a real question rather than a formality.

Before the pour: formwork has to be built for the loads it will see

Removal is only half of 1926.703. The earlier paragraphs set the conditions that make removal a controlled event rather than a surprise. Under (a)(1), formwork shall be designed, fabricated, erected, supported, braced and maintained so that it will be capable of supporting all vertical and lateral loads that may reasonably be anticipated to be applied to it. Lateral loads are the part owners forget. Wet concrete pushes sideways, and workers, vibrators and equipment add loads of their own.

Paragraph (a)(2) adds a documentation requirement that is easy to meet and easy to skip: drawings or plans, including all revisions, for the jack layout, formwork (including shoring equipment), working decks, and scaffolds shall be available at the jobsite. If your crew builds from a rental supplier's layout, a sketch, or memory, ask whether the drawings on site match what is standing. A revision that changed the shore spacing but never reached the field is exactly the kind of gap this paragraph is aimed at.

Shoring inspections happen at three moments, not one

Paragraph (b) is a run of short, specific duties about shoring equipment, including equipment used in reshoring. Read in order, they describe a sequence.

Before erection, under (b)(1), all shoring equipment shall be inspected to determine that it meets the requirements specified in the formwork drawings. Damaged equipment is dealt with in (b)(2): shoring equipment found damaged such that its strength is reduced to less than the formwork must have shall not be used for shoring. That is a quarantine rule. A bent leg or a crushed base plate is not something to use because the pour starts in an hour.

Then comes the part that surprises people who assume an inspection is a single event. Under (b)(3), erected shoring equipment shall be inspected immediately prior to, during, and immediately after concrete placement. That is three moments around the pour, and the one during placement is the most demanding because it means someone has to be watching the shoring while the concrete is going in, with the authority to act. If equipment is found damaged or weakened after erection such that its strength is reduced below what the formwork requires, (b)(4) says it shall be immediately reinforced. The standard does not say to note it for later.

A small crew can meet this by deciding in advance who is the person watching the shores during the pour, giving that person nothing else to do at that point, and giving them the authority to stop the placement. How you record those three inspections is your choice. The standard states the duty to inspect; keeping a short dated note is simply how a business shows afterward that it happened.

The details of how shores sit

The remaining shoring paragraphs are about how equipment bears on the ground and on the form, and they read like a list of the ways a shoring system quietly goes wrong.

Sills for shoring shall be sound, rigid, and capable of carrying the maximum intended load, per (b)(5). A shore is only as good as what it stands on, and a sill set on soft or disturbed ground defeats a perfectly good shore. Under (b)(6), all base plates, shore heads, extension devices, and adjustment screws shall be in firm contact, and secured when necessary, with the foundation and the form. A shore that has drifted slightly out of contact is not carrying load, which pushes more onto its neighbors.

Paragraph (b)(7) prohibits eccentric loads on shore heads and similar members unless those members have been designed for such loading. An eccentric load is one that is off-center on the member, and the practical way it shows up is a shore head that has shifted or a form that has been jacked unevenly. Paragraph (b)(8) then sets specific requirements, in addition to the general ones, for single post shores used one on top of another, which is the tiered arrangement. If your crew ever stacks single post shores to reach a higher deck, read that paragraph in full before it happens, because the added requirements are specific to that arrangement and a summary here would not substitute for them.

What this means for a small contractor

A useful way to hold all of this is as a short set of questions someone must be able to answer for each pour. What do the drawings say about removal, and are they the current revision? If we plan to strip early, what test will tell us the concrete is ready, and when will the result be in hand? Who inspects the shoring before erection, around the pour, and during it? And when the reshoring question comes up, what loads are actually on that slab today?

None of those require a safety department. They require that the person who runs the pour treats removal as a decision with an input, not a point on the schedule. A schedule that depends on stripping forms by a certain day is a schedule that has quietly made the safety decision for you, and 1926.703(e)(1) exists to put that decision back where someone is accountable for it.

Reading a standard and following a post about it does not make a job compliant. Site conditions, project specifications, engineered designs, and state or local requirements all matter, and a qualified person familiar with your project should confirm how these rules apply to your pour.

General guidance only, not legal advice. Verify requirements against the current text of 29 CFR 1926.703 and consult a qualified professional about your project.

Related reading: Concrete and Masonry Work: The OSHA Subpart Q Rules Small Contractors Keep Missing | Jobsite Inspections and the Competent Person Under 1926.20

OSHA standards cited

Always verify current OSHA standards at osha.gov. This article reflects standards in effect at the date of publication.