Temporary Heaters on Winter Jobsites: What 29 CFR 1926.154 Requires for Clearance, Ventilation and Fuel
29 CFR 1926.154 sets the rules for jobsite heaters: fresh air, clearance from combustibles and tarps, level setup and fuel controls. A guide for small crews.
The drywall crew shows up to a framed-in house on a morning when the water in the bucket has a skin of ice on it. Before anyone hangs a sheet, somebody fires up the torpedo heater, points it down the hallway, and tacks plastic over the window openings so the heat stays in. By nine the mud is workable and the house is warm. Nobody has thought about where the exhaust is going, how close the heater is to the stack of insulation by the stairs, or whether the poly on the windows is close enough to the flame to matter. Every one of those questions has an answer in the construction standards, and it is not a long one.
This post answers a single question: what does 29 CFR 1926.154, the construction standard titled "Temporary heating devices," require when you heat a jobsite? It is not about space heaters in a shop or an office, which OSHA handles under the electrical and general duty rules we cover in our post on portable space heaters at work. And it is not about how to store the propane cylinders that feed many jobsite heaters, which is the subject of our post on propane storage under 1910.110, including the separate construction rule in 1926.153. Here the heater is already running on your site, and the question is what has to be true around it.
Where 1926.154 sits and what it covers
Section 1926.154 is part of Subpart F of the construction standards, the fire protection and prevention subpart. That placement tells you how OSHA thinks about jobsite heaters: as a fire source first and an air quality problem second. The section is short. It covers five things: ventilation, clearance from combustibles and how heaters are mounted, stability, a flat ban on solid fuel salamanders in certain places, and controls on oil-fired heaters.
It applies to temporary heating devices used in construction work. That means the propane torpedo heater in the stairwell, the kerosene or diesel forced-air unit blowing into a tented foundation, the radiant heater on a stand warming a crew at the cut station, and the indirect-fired unit pushing heat through a duct into an enclosed floor. If it produces heat to make winter work possible and it is not part of the building's permanent system, assume this section is the one an inspector will read.
Fresh air comes first
Paragraph (a)(1) is the broadest requirement in the section. It says that fresh air must be supplied in sufficient quantities to maintain the health and safety of workers, and that where natural means of fresh air supply are inadequate, mechanical ventilation must be provided. Paragraph (a)(2) adds that when heaters are used in confined spaces, special care must be taken to provide sufficient ventilation to ensure proper combustion, maintain the health and safety of workers, and limit temperature rise in the area.
Notice what the standard does not give you. There is no cubic-feet-per-minute figure and no rule of thumb about how many windows must stay open. It is a performance requirement: the air has to be good enough to keep people healthy. That puts the judgment on you, and it is exactly the judgment that gets lost the moment someone hangs plastic over the openings to hold heat in.
The reason this matters is that direct-fired heaters, the common torpedo and salamander types, release their combustion products straight into the space they are heating. Carbon monoxide is the obvious concern, and it gives no warning that a worker can smell or see. The construction standard on gases, vapors, fumes, dusts, and mists, 1926.55, separately limits employee exposure to air contaminants, and carbon monoxide is one of them. A heater that runs fine in an open-sided frame can become a real exposure problem once the same building is closed in for drywall or paint. Our general post on carbon monoxide hazards covers symptoms and monitoring in more depth.
For a small crew, a practical approach is to decide ventilation when you decide the enclosure. If you are going to tent or poly a space, someone should also decide how air gets in and exhaust gets out, whether an indirect-fired heater that vents outside would be the better tool for a tight space, and whether a personal carbon monoxide monitor should be on the person working closest to the heater. The words "confined spaces" in (a)(2) are worth taking seriously too. A crawlspace, a basement with one door, or a small mechanical room does not have to meet the formal permit-space definition in Subpart AA to be a place where a heater can use up the good air quickly.
Clearance from combustibles and from tarps
Paragraph (b) is the part with real numbers, and they come from the standard itself. Under (b)(1), temporary heaters must be installed at least the distance shown in Table F-4 from combustible material. For circulating-type room heaters, that table calls for 12 inches at the sides and rear and 18 inches from the chimney connector. For radiant-type room heaters, it is 36 inches at the sides and rear and 18 inches from the chimney connector. Paragraph (b)(2) allows heaters that are specifically designed and approved for smaller clearances to be installed at those smaller distances, which in practice means the manufacturer's listed clearances on the data plate.
That second paragraph cuts both ways. Many forced-air construction heaters carry manufacturer clearance figures in front of the outlet that are far larger than anything in the table, because the hot air stream is the whole point of the machine. Read the plate and the manual before you decide how close the heater can sit to the insulation, the lumber stack, or the cardboard packaging from the cabinets that were delivered yesterday. The table is the floor, not the plan.
Paragraph (b)(3) addresses the floor itself. Heaters not suitable for use on wood floors must be set on suitable heat-insulating material or at least one inch of concrete or equivalent, and that material must extend at least two feet in all directions beyond the edge of the heater. On a wood-framed project, this is the requirement most likely to be missed, because the subfloor is the only surface available and nobody thinks of it as fuel.
Paragraph (b)(4) is the one that speaks most directly to winter enclosures. Heaters used near combustible tarpaulins, canvas, or similar coverings must be located at least 10 feet from those coverings, and the coverings must be securely fastened to prevent them from igniting or upsetting the heater because of wind action. Wind is the detail people forget. A tarp that sits well clear of the heater at seven in the morning can flap into the outlet at noon when the weather turns, and a loose cover can knock over a heater that was standing on uneven ground.
Level, stable, and the right kind of heater
Paragraph (c) requires heaters, when in use, to be set horizontally level unless the manufacturer's markings permit otherwise. That sounds trivial until you remember where heaters actually get set down: on a frozen rut, on a pile of sheathing offcuts, on a stair landing. A heater that is not level can burn unevenly, spill fuel, or tip when someone brushes it. Treat "level and stable" as part of placing the heater, not something to fix later.
Paragraph (d) is the bluntest line in the section. Solid fuel salamanders are prohibited in buildings and on scaffolds. Burning wood or coal in an open container to warm a crew may still happen on some sites, and it is not allowed inside the structure or up on the scaffold, full stop.
Paragraph (e) covers oil-fired heaters. Flammable liquid-fired heaters must be equipped with a primary safety control to stop the flow of fuel in the event of flame failure, and the standard specifies that barometric or gravity oil feed is not considered a primary safety control. Heaters designed for barometric or gravity oil feed may be used only with the integral tanks. Heaters specifically designed and approved for use with separate supply tanks may be directly connected for gravity feed or an automatic pump from a supply tank. In plain terms, check that the kerosene or diesel heater on your site actually shuts off fuel if the flame goes out, and do not rig up a bigger fuel supply to a heater that was not built for one.
Turning the standard into a winter routine
A standard this compact is easy to read and hard to follow every single day, because heaters get moved constantly. They follow the work from room to room, and each move is a new placement decision made by whoever is cold.
The fix is to make placement a named job. Pick one person on each site, usually the lead, who places and moves heaters and who checks four things each time: the clearance to combustibles and to any tarp or poly, the surface underneath, whether the unit is level, and how fresh air is getting in now that the space has changed. That person should also know where the fuel is stored and how much is inside the building, which brings 1926.153 back into the picture for propane.
Training is not optional here either. Section 1926.21(b)(2) requires the employer to instruct each employee in the recognition and avoidance of unsafe conditions and the regulations applicable to the work environment. On a winter job, that instruction should cover what carbon monoxide exposure feels like, why nobody covers a heater's intake or outlet to "hold the heat," and who to tell when a heater is acting strangely. Our post on competent person jobsite inspections under 1926.20 explains how a heater check can ride along with the frequent inspections you already make, and a fire extinguisher near every heater fits naturally with the construction fire protection program in 1926.150.
None of this makes a site compliant on its own, and the standard is only one of several that apply when you heat an enclosed construction space. But most heater problems on small jobs come from the same few shortcuts: a tarp that crept too close, a heater on bare subfloor, a space closed in without anyone deciding where the exhaust goes. Name the person, write the four checks on the site board, and read the data plate before the first cold morning rather than after.
Related reading: Portable Space Heaters at Work | Propane Storage Under 1910.110 | Carbon Monoxide Hazards
OSHA standards cited
- 29 CFR 1926.154
Construction Industry Standards
- 29 CFR 1910.110
General Industry Standards
- 29 CFR 1926.153
Construction Industry Standards
- 29 CFR 1926.55
Construction Industry Standards
- 29 CFR 1926.21
Construction Industry Standards
- 29 CFR 1926.20
Construction Industry Standards
- 29 CFR 1926.150
Construction Industry Standards
Always verify current OSHA standards at osha.gov. This article reflects standards in effect at the date of publication.
Not sure where you stand?
Take the 5-minute compliance assessment. Answer a few questions about your business and get a prioritized list of what OSHA expects, free.
Related Articles
Continue learning about OSHA compliance and workplace safety
Construction Safety
The Saw on the Tailgate: What OSHA 1926.304 Requires of the Circular Saws and Table Saws Your Crew Brings to the Job
29 CFR 1926.304 sets guard rules for jobsite woodworking tools: lower guards on circular saws, hoods on table saws, and lockable switches on fixed tools.
Construction Safety
The Tenant Is Still Working Upstairs: What OSHA 1926.34 Requires of Your Crew's Exits
OSHA 1926.34 requires free, unobstructed, marked exits in any occupied building. See what that means when your crew works inside a space people still use.
Construction Safety
Who Decides the Concrete Is Ready? Stripping Forms and Shores Under OSHA 1926.703
OSHA 1926.703 bars removing forms and shores until the employer determines the concrete is strong enough. See what that rests on and when shoring is inspected.