Brick, Block, Bagged Cement and Lumber: The Stacking Limits OSHA 1926.250 Sets for Jobsite Material Storage
OSHA 1926.250 sets stacking limits for brick, block, bagged material and lumber, plus floor load and edge setbacks. What small contractors must do on site.
A delivery truck drops three pallets of block, a unit of lumber and a stack of bagged mortar mix at a small commercial job on a Friday afternoon. The driver wants to be gone, the foreman is on the phone, and the only open space is along the edge of the second-floor slab, close to where the exterior wall stops. The pallets go there, because that is where the forklift could reach. By Monday the stack has been added to twice, and nobody has asked how much weight that slab edge is carrying or what happens if a pallet shifts.
This post answers one narrow question: what does 29 CFR 1926.250, the construction standard titled General requirements for storage, actually require of the way you stack and place materials? It does not cover debris and scrap removal, which is a separate standard; our post on jobsite housekeeping under 1926.25 handles that question.
The rule that applies to every pile
Paragraph (a)(1) is the foundation. Materials stored in tiers must be stacked, racked, blocked, interlocked or otherwise secured to prevent sliding, falling or collapse. The standard does not say which method you must use. It sets an outcome, and the method is your choice: cribbing under a stack, banding, interlocking courses, racking, or blocking at the ends.
That outcome-based wording matters when you think about how an inspector reads a jobsite. A stack of material that leans, sits on soft or uneven ground, or has been built higher by whoever had a free minute is a stack that is not secured against falling. You do not need a specific number to see the problem, and neither does a compliance officer.
Paragraph (a)(3) adds that aisles and passageways must be kept clear so material handling equipment and workers can move safely, and kept in good repair. Paragraph (a)(4) deals with changes in level: where road or working levels differ, you need ramps, blocking or grading so vehicles can move between them safely. A pile that blocks the only path for the telehandler is a (a)(3) problem as much as a stacking problem.
Floors are not unlimited shelves
Paragraph (a)(2) covers the weight of what you put on floors within buildings and structures. The weight of stored materials must not exceed the maximum safe load limits of the floor, and employers must conspicuously post those limits, in pounds per square foot, in all storage areas. Two exceptions are written into the text: storage on a floor or slab on grade needs no posting, and the posting requirement does not apply to storage areas in single-family residential structures or wood-framed multi-family residential structures.
For a small contractor working in a renovation or tenant build-out, this is the part most often overlooked. Pallets of tile, drywall or block are heavy, and a framed or newly poured upper floor may not be ready for them. The standard does not tell you how to learn the safe load of a given floor. That is a question for the engineer or designer of record, and you should ask before the delivery arrives, not after it has been placed.
Setbacks from edges and openings
Paragraph (b)(1) says material stored inside buildings under construction must not be placed within 6 feet of any hoistway or inside floor opening, and not within 10 feet of an exterior wall that does not extend above the top of the stored material. The Friday-afternoon pile at the slab edge in the opening scenario is exactly what this paragraph is aimed at. Material close to an unprotected edge can be knocked off, and a falling object is a struck-by hazard for anyone below.
Two other paragraphs belong in the same conversation. Paragraph (b)(5) says materials must not be stored on scaffolds or runways in excess of supplies needed for immediate operations. If a scaffold platform has become the place where the day's leftover material waits for tomorrow, it is carrying more than the standard allows. And paragraph (b)(2) requires that employees working on stored material in silos, hoppers, tanks and similar storage areas be equipped with personal fall arrest equipment meeting the requirements of Subpart M.
The numbers for brick, block, bags and lumber
Several paragraphs give specific limits for common materials, and these are the ones worth printing and posting in the site trailer.
Bagged material, under (b)(4), must be stacked by stepping back the layers and cross-keying the bags at least every 10 bags high. Cross-keying means turning the pattern so each layer locks into the one below it, which is what keeps a tall stack of bags from sliding as a unit.
Brick, under (b)(6), may not be stacked more than 7 feet high. When a loose brick stack reaches 4 feet, it must be tapered back 2 inches in every foot of height above the 4-foot level. Masonry blocks, under (b)(7), must be tapered back one-half block per tier when the stack is higher than 6 feet.
Lumber is covered by paragraph (b)(8). Used lumber must have all nails withdrawn before stacking. Lumber must be stacked on level and solidly supported sills, and stacked so it is stable and self-supporting. Lumber piles may not exceed 20 feet in height, and lumber that will be handled manually may not be stacked more than 16 feet high. Structural steel, poles, pipe, bar stock and other cylindrical materials, unless racked, must be stacked and blocked to prevent spreading or tilting, under (b)(9).
Paragraph (b)(3) is short and easy to overlook: noncompatible materials must be segregated in storage. The standard does not define which materials are incompatible. Cement bags beside open containers of solvent, or fuel containers beside oxidizers, are the kinds of pairings a careful supervisor would keep apart, and the manufacturer's safety data sheet will usually say what a product should not be stored near.
Why shrink-wrapped pallets do not end the question
Contractors sometimes assume that material delivered banded or shrink-wrapped on a pallet is exempt from stacking limits because the supplier already secured it. OSHA has addressed whether the brick and masonry block limits in 1926.250 apply to materials that remain completely secured as shipped, in a letter of interpretation dated February 6, 2008. Read that letter, and the current text of the standard, before relying on an exemption. Once you break the bands, restack, or build a stack taller than what was delivered, the limits in the paragraphs above are the ones you are working against.
Making this routine on a small crew
Most of what 1926.250 asks for can be handled with a few habits rather than a program. Decide where deliveries go before they arrive, and tell the supplier. Walk the site at the end of each day and look at every stack as a competent person would: is it level, is it secured, is it clear of edges and openings, is it blocking a path? If a stack has been built up past the limit, take it down. Write down the floor load limits you were given and post them where the material is stored.
If you already document daily jobsite checks, add a line for stored materials. Our post on competent person jobsite inspections under 1926.20 explains how the frequent inspections that standard calls for can carry this kind of check.
Following these paragraphs does not make a jobsite compliant on its own, and this post is not legal advice. Check the current text of 29 CFR 1926.250 and any state plan rules that apply to you, and ask a qualified professional about your specific site and floors.
Related reading: Jobsite Housekeeping Under 1926.25 | Competent Person Jobsite Inspections Under 1926.20 | Guardrail Systems Under 1926.502(b)
OSHA standards cited
- 29 CFR 1926.250
Construction Industry Standards
- 29 CFR 1926.25
Construction Industry Standards
- 29 CFR 1926.20
Construction Industry Standards
- 29 CFR 1926.502
Construction Industry Standards
Always verify current OSHA standards at osha.gov. This article reflects standards in effect at the date of publication.
Not sure where you stand?
Take the 5-minute compliance assessment. Answer a few questions about your business and get a prioritized list of what OSHA expects, free.
Related Articles
Continue learning about OSHA compliance and workplace safety
Construction Safety
The Saw on the Tailgate: What OSHA 1926.304 Requires of the Circular Saws and Table Saws Your Crew Brings to the Job
29 CFR 1926.304 sets guard rules for jobsite woodworking tools: lower guards on circular saws, hoods on table saws, and lockable switches on fixed tools.
Construction Safety
Temporary Heaters on Winter Jobsites: What 29 CFR 1926.154 Requires for Clearance, Ventilation and Fuel
29 CFR 1926.154 sets the rules for jobsite heaters: fresh air, clearance from combustibles and tarps, level setup and fuel controls. A guide for small crews.